REFERENCE PROJECTS
TURKCELL – EUROPE DATA CENTER
ÇORLU, TURKEY
Client: TURKCELL Makine
Completion: December, 2020
Reference: **Company reference
(KLE Engineering)
Description of Work:
-
The Project located in ÇORLU - TURKEY
-
43.000 sqm project area, 6.800 sqm w, TIER 3 Certified, LEED GOLD Green Building Certified
IMPRO-CENGİZ MAKİNE
Gebze,TURKEY
Client: IMPRO-Cengiz Makine
Completion: May, 2018
Reference: **Company reference
(KLE Engineering)
Description of Work:
-
Project management and consultancy including design, procurement, installation, commissioning,
-
Contract management, claim management.
INTERNATIONAL TURKMENBASI SEAPORT PROJECT
Turkmenbasi,TURKMENISTAN
Client: The State Service of
Marintime & River
Transportation of Turkmenistan
Completion: May, 2018
Reference: *Personal references
Description of Work:
-
The project ‘Turkmenbasi Seaport’ scope is not only important for the EPC scope of below mentioned terminals,
-
Ferry and passenger terminal,
-
Container terminal,
-
General cargo port,
-
Bulk cargo port,
-
Ship building and repair facility are built,
-
Ro-Ro and polypropylene terminal is expanded,
-
But also, by the budget of $ 1.5 billion is constructed as the biggest seaport of the Caspian Sea.
GARABOGAZ AMMONIA AND UREA PRODUCTION
Garabogaz,TURKMENISTAN
Client: Turkmenistan Ministry
of Chemistry
Completion: June, 2018
Reference: *Personal references
Description of Work:
-
Annual production capacity of 1.155.000 tons,
-
Budget of $ 1.35 billion,
-
The biggest ammonia & urea production plant of Turkmenistan.
0,8 mtpy NEW BAR ROLLING MILL PROJECT / LIBYA
Client: LISCO – LIBYAN IRON AND STEEL COMPANY
Completion: September, 2016
Reference: *Personal references
Description of Work:
-
The project located in Misurata – LIBYA , Mainly consist of two part;
-
Reconditioning of the existing Facilities
-
Balance Erection Works of 0,8 mtpy New Bar Rolling Mill Facility ( Mechanical , Electrical & Instrumentation Erection Works & Piping including Cold Tests and Commissionig assistance Works.)
CONSTRUCTION OF CONTAINER TERMINAL PROJECT / LIBYA
Client: Misurata Free Zone Administration
Completion: May, 2014
Reference: *Personal references
Description of Work:
-
Construction of berths for the berthing up to 81.000 DWT Container Vessels.
-
The Deck Structure; steel pipe pile foundadtions supporting a combined precast and in-situ concrete structure.
-
The total length of the berth is : 800 mt.
-
The Works performed for the construction of the berths as follows :
-
Fabrication of two Jack-up barges ( 400 ton capacity each ) including detailed design.
-
Construction of 589 mt. Long berths with 696 pcs of piles, each 48 ‘’ diameter with 20 mm thickness and min 36 mt. in length , supporting a combined precast and in-situ concrete deck structure.
-
Extention of 211 mt. Long existing berths with 102 pcs of piles on the sea side each 48 ‘’ diameter with 20 mm thickness and min. 36 mt. in length süpporting a combined precast and inüsitu concrete deck structure and 54 pcs of bored piles on the Land side each 1.000 mm diameter and 15 mt. in length supporting SSG Crane Beams.
-
Supplying and Installation of rubber fenders.
-
Applying Catodic Protection to all exposed ferrous members includ. Steel Piles
-
Supplying and Installation of Crane Rails
BISKRA 230 MW SCPP PROJECT
ALGERIA
Client: SONELGAZ – ALGERIA SONELGAZ(National Society for Electricity and Gas ) - ALGERIA
Completion: June, 2017
Reference: *Personal references
Description of Work:
-
Complete Electrical, Mechanical and Instrumentation Installation Works of 230 MW Gas Turbine PP
1450 MW MOSTAGANEM PP COOLING WATER INTAKE SYSTEM / ALGERIA
Client: SONELGAZ - ALGERIA
Completion: In progress
Reference: *Personal references
Description of Work:
-
The Scope of Project is installation of Cooling Water Intake Pipeline
-
( 5 ea x 2000 mt. , HDPE Pipes with 2500 mm diameter ) including precast concrete intake head structures as well as discharge unit for 1450 MW Combined Cycle Power Plant Project at MOSTAGANEM - ALGERIA
BAKU SHIPYARD PROJECT / AZERBAIJAN
Client: BAKU SHIPYARD LLC
Completion: September, 2013
Reference: *Personal references
Description of Work:
-
Construction of 4 building in Baku Shipyard Project
-
Total Area is : 44.000 m2 . Two Steel Structure Building ( 28.200 m2 ) and three reinforced concrete building ( 15.800 m2 )
-
The Total Weight of Fabricated and Installed Steel Structure is : 6.500 Ton includ. Detailed Design and Shop drawings.
KARBELA 300 MW POWER PLANT
IRAQ
Client: Ministry of Electricity - IRAQ
Completion: Junei 2012
Reference: *Personal references
Description of Work:
-
Turnkey Construction of 300 MW Diesel Power Plant Including all Civil, Mechanical, Electrical & Infrastructural Works.
DIWANIYAH 200 MW POWER PLANT
IRAQ
Client: Ministry of Electricity - IRAQ
Completion: July, 2012
Reference: *Personal references
Description of Work:
-
Turnkey Construction of 200 MW Diesel Power Plant including all Civil , Mechanical , Electrial & Infrastructural Works.
VLORE 1x100 MW CCPP
Vlore,ALBANIA
Client: KESH Albanian Power
Corporation
Completion: September, 2009
Reference: *Personal references
Description of Work:
-
Complete Mechanical Erection , Piping, Insulation and Painting Works of 100 MW Single-Shaft Combined
-
Cycle Power Plant.
-
Gas Turbine, Steam Turbine, Generator and auxiliaries (Supplied by Ansaldo-Italy)
-
HRSG (Supplied by Nooter Ericsen – Italy)
-
Condenser (Supplied by Ofmeco– Italy)
-
Piping and Supports (Fabrication, Erection, PWHT, NDT, Painting ,Insulation, Testing)
-
BOP Equipments and Systems i.e. Water Treatment Plant, Sea Water Pumps, Fuel Oil Storage, etc
-
4300 m. API 5L Fuel Oil Piping for Offshore connection between CBMS and Site (Welding and NDE testing)
SUMGAIT 500 MW CCPP
Sumgait,AZERBAIJAN
Client: AZENERJI JSC.
Completion: May, 2007
Reference: *Personal references
Description of Work:
-
Manufacturing and assembly of two heat recovery steam generators (including design and supply)
AKENERJI CCPP
İzmir,TURKEY
Client: AKENERJI
Completion: December, 2004
Reference: *Personal references
Description of Work:
-
Complete Mechanical and Instrument Erection Works of 2 Heat Recovery Steam Generators and associated equipment
-
32 Tons piping including supports and valves
-
Instrument Installation
-
Supply and installation of Insulation
-
NDT, PWHT services
KARADAKH GCSB
Karabakh,AZERBAIJAN
Client: AZERGAZ A.Ş
Completion: August, 2003
Reference: *Personal references
Description of Work:
-
Complete Mechanical / Electrical / Control & Instrumentation Erection Works of Gas Compressor Station also including
-
Supply of all structural steelwork for compressor building and pipe racks
-
Design, supply and fabrication of fire works storage tank
-
Supply and fabrication of vent stack
SEVERNAYA 400 MW
COMBINED CYCLE POWER PLANT
Severnaya,AZERBAIJAN
Client: Joint Stock Company AZENERJI
Completion: November, 2002
Reference: *Personal references
Description of Work:
-
Complete mechanical, electrical control and instrumentation erection works of 400 MV single-shaft.
-
Combined cycle pover plant (including structural steel works of GB building, pumphouse and underground.
-
CW pipeline.
ESKISEHIR INDUSTRIAL
POWER CCPP
Eskisehir,TURKEY
Client: Eskisehir Industrial Power
Generation Autoproductor
Group Co.
Completion: April, 2001
Reference: *Personal references
Description of Work:
-
Complete electrical and instrumentation installation works of main compressor ststion and booster compressor station.
TUPRAS CCR &
ISOMETRIZATION PLANT PROJECT
Aliaga,İzmir,TURKEY
Client: TUPRAS, Turkish Petroleum
Refineries Corp.
İzmir Refinery
Completion: September, 2000
Reference: *Personal references
Description of Work:
-
CCR & Isometrization plant project, spool fabrication and erection works of underground and aboveground pipe lines including;
-
645 tons ON site aboveground piping erection,
-
285 tons OFF site avoveground piping erection,
-
215 tons ON site aunderground piping fabrication and erection,
-
11 tons pipe support fabrication and erection.
TOMSKNEFT GCS
Leuginetskoye, Western Siberia, RUSSIA
Client: OAO TOMSKNEFT VNC
Completion: November, 1998
Reference: *Personal references
Description of Work:
-
Complete Electrical and Instrumentation Installation Works of Main Compressor Station and Booster Compressor Station including;
-
6 no. Power Transformers and Diesel Generators.
-
134 no. MV,LV Switchgears and MCC’s and HT panels.
-
1315 no. Lighting Fixtures including Poles, Supports and Accessories.
-
262 km. Power & Control and Instrument Cables including Terminations.
-
22 km. Heat Tracing Cables and complete HT Systems.
-
25 km. Cable Ladders, Trays and Conduits.
-
3120 no. Field Instruments including Calibration and Loop Checks.
-
8 km. Instrument Impulse Piping & 30 no. Instrument Panels (DCS & ESD Systems).
-
UPS, Power Metering and Monitoring Systems, Complete Lightning Protection & Grounding Systems.
-
Fire & Gas Detection Systems, Telephone & Communication Systems.
ÇAYELİ COPPER WORKS INC.
PASTEFILL PLANT
Rize, TURKEY
Client: Çayeli Copper Works Inc.
Completion: March, 1999
Reference: *Personal references
Description of Work:
-
Civil Construction and Mechanical , Electrical and Instrumentation Erection Works of Paste fill Plant including;
-
Complete Civil Works.
-
Supply, Fabrication and Erection of a Three Storied Steel Building.
-
Supply, Fabrication and Erection of an Elevated Steel Thickener Tank and an Agitated Storage tank.
-
Mechanical Erection of all Plant Equipment.
-
Supply and Erection of Victaulic Grooved Piping and Utility Piping Systems.
-
Supply of Power & Control and Instrument Cables, complete Plant Instruments, Lighting Fixtures.
-
Complete Electrical and Instrumentation Erection Works.
-
Modification Works to existing Thickeners and Tailings Disposal System.
NUH CIMENTO COMBINED CYCLE POWER PLANT
Hereke, TURKEY
Client: Nuh Çimento A.Ş.
Completion: October, 1999
Reference: *Personal references
Description of Work:
-
Complete Mechanical, Electrical & Instrumentation Works of one HRSG for LM 2500+ type Gas Turbine and all External Piping Work including;
-
HRSG contains about 285 tons of Pressure Part and 253 tons of Non-Pressure Part.
-
External Piping total weight (alloy, SS and CS) is about 27 tons.
-
Pipe Rack and Pipe Support weight is about 25 tons.
-
Heaviest Single Piece in this project was the Heating Module (140 tons) which was handled by one 440 t. and one 330 t. Hydraulic Mobile Cranes together.
-
Complete Electrical and Instrumentation Installations.
EEE GAS TURBINE POWER PLANT 1x40 MW
Eskişehir, TURKEY
Client: Eskisehir Industrial Power Generation Auto Production Group Co.
Completion: April, 1998
Reference: *Personal references
Description of Work:
-
Complete Mechanical, Electrical & Instrumentation Installation Works of a Frame 6 type Gas Turbine Power Plant (The first stage of the Combined Cycle Power Plant) including;
-
328 tons Mechanical and Electrical Equipment.
-
10 tons Piping.
-
3 tons Power & Control Cables.
-
Complete NDT Services.
TENGIZCHEVROIL KTL 2.3 EXPANSION PROJECT PIPE SPOOLS FABRICATION
İstanbul, TURKEY
Client: Tengizchevroil
Completion: November, 1998
Reference: *Personal references
Description of Work:
-
Fabrication of Pipe Spools for the Interconnecting Piping System of 4 no.’s ..of.FM type Utility B Boilers and Pipe Connections to Water Deminerilazition ..Plant including; ..
-
80 tons Pipe Spools ( Pipe diameters.range from 2” to 14”).
-
Complete NDT Services.
-
Painting of Pipe Spools.